The project Emils Bro

Our project Emils Bro continues! Right now, the assembly of the loadbearing structure of floor six is continuing. Next week, the assembly will continue to floor nine. In about two weeks, preparing installations will begin. The loadbearing structure and roof are planned to be finished during the first week of July, week 28. Construction of structures and installations inside the building and facade will begin in August and continue until January 2021. The first tenants are planned to move in during February 2021!